ಇಂದಿನವರೆಗೆ ಪ್ರಗತಿ...
ಯೋಜನೆ | ಮಂಜೂರಾದ ಉದ್ದ(ಕಿಮಿ) | ಪೂರ್ಣಗೊಂಡ ಉದ್ದ(ಕಿಮಿ) | ಮಂಜೂರಾದ ಕಾಮಗಾರಿಗಳ ಸಂಖ್ಯೆ | ಪೂರ್ಣಗೊಂಡ ಕಾಮಗಾರಿ ಗಳ ಸಂಖ್ಯೆ | ವೆಚ್ಚ (ಕೋಟಿಗಳಲ್ಲಿ) |
5054 Special Grant | 278.17 | 188.99 | 384 | 333 | 86.90 |
5054Special Grant(150Cr and 65.6 Cr) | 408.62 | 392.57 | 176 | 168 | 144.28 |
5084 | 17.73 | 0.00 | 3 | 0 | 0.00 |
Colony Roads | 495.78 | 463.61 | 1103 | 1058 | 246.41 |
DC Grant | 5.69 | 5.30 | 4 | 4 | 1.75 |
Flood Damages | 606.32 | 554.67 | 376 | 361 | 193.06 |
HKRDB | 971.99 | 253.85 | 227 | 209 | 149.99 |
Lumpsum Grant | 96.24 | 90.59 | 54 | 52 | 22.67 |
NGNRY II | 5722.03 | 5487.06 | 2208 | 2145 | 2152.39 |
NGNRYII(Additional) | 7.00 | 8.65 | 3 | 3 | 4.08 |
NGNRYII(Change of work) | 73.05 | 73.33 | 40 | 40 | 29.31 |
NGNRYIII | 3866.34 | 3721.08 | 1566 | 1505 | 2101.47 |
NGNRYIII(Additional) | 352.56 | 326.57 | 138 | 134 | 212.62 |
NGNRYIII(Change of work) | 76.96 | 69.80 | 37 | 34 | 37.54 |
NGNRY-IV | 4477.89 | 4291.23 | 1666 | 1615 | 3204.33 |
NGNRYIV(Additional) | 365.60 | 351.15 | 151 | 145 | 324.25 |
NGNRYIV(Change of work) | 74.09 | 69.37 | 27 | 25 | 34.95 |
PMGSY | 35.20 | 7.24 | 9 | 3 | 0.00 |
PMGSY I (DDP) | 8.75 | 0.00 | 5 | 0 | 0.00 |
PMGSY II | 847.29 | 241.30 | 122 | 58 | 84.09 |
PMGSY III | 8768.44 | 5206.02 | 968 | 844 | 3509.99 |
PMGSY INCENTIVE | 2298.22 | 2118.88 | 539 | 498 | 215.45 |
PMGSY SAVINGS | 696.89 | 660.92 | 148 | 144 | 66.66 |
Reserve Constituency | 21.44 | 20.16 | 13 | 13 | 12.77 |
SCP | 22.92 | 21.99 | 17 | 17 | 10.46 |
SCP/TSP | 437.83 | 410.09 | 231 | 213 | 331.60 |
SDP | 572.60 | 552.69 | 436 | 429 | 315.39 |
SDP(Change of work) | 0.52 | 0.40 | 1 | 1 | 0.20 |
SDP1819 | 404.48 | 397.85 | 187 | 185 | 223.77 |
SDP1920 | 486.66 | 472.52 | 232 | 227 | 249.31 |
SDP2018-19 | 21.45 | 19.66 | 14 | 13 | 10.74 |
SDP2020-21 | 78.33 | 73.12 | 46 | 44 | 24.32 |
SDP2021-22 | 502.54 | 475.00 | 257 | 245 | 243.47 |
SDPChange of work | 4.10 | 4.10 | 3 | 3 | 2.82 |
Select.. | 3.30 | 0.00 | 1 | 0 | 0.00 |
TSP | 7.23 | 6.71 | 5 | 5 | 2.92 |
| | | | | |